Dear colleague, welcome to the first "PM question of the week" for 2015!

Let's kick start the new year testing your knowledge about project procurement management.

Which of the following options is not necessary to develop a SOW?
a. Signed contract.
b. Project schedule.
c. Scope baseline.
d. Cost estimates.

Answer to question and explanation

The correct answer is a. Signed contract.

Explanation: the logic behind this question is quite simple. First of all, in order to develop a Statement Of Work, that is that part of a procurement documents describing the goods or services to be purchased, you need to factor in the time, cost and schedule constraints of the project, that is options b. c. and d. are all necessary. Moreover
a. Signed contract. is clearly wrong because in order to produce a contract you need the SOW in the first place.

Add new comment

You must have JavaScript enabled to use this form.

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.