PM Question of the Week - week 4 2015

Dear colleague, welcome to the "PM question of the week" newsletter # 4 2015.

This week newsletter is about the project management basics.

What is the most important output of the Direct and Manage Project Work process?
a. The activity schedule.
b. The scope baseline.
c. The project deliverables.
d. Change requests.

Answer to question and explanation

The correct answer is c. The project deliverables.

Explanation: deliverables are the products of the project and Direct and Manage Project Work is the project management process that outputs them, according to the project management plan and objectives.

Add new comment

You must have JavaScript enabled to use this form.

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.