PM Question of the Week - week 5 2015

Dear colleague, welcome to the "PM question of the week" newsletter # 5 2015.

We propose you another question covering some of the project management basics.

Which of the following options does not include only project management constraints?
a. Schedule, budget, risk.
b. Resources, budget, results.
c. Resources, quality, scope.
d. Budget, risk, quality.

Answer to question and explanation

The correct answer is b. Resources, budget, results.

Explanation: results are not a project constraint, but rather an output. Project constraints are: scope, schedule, budget (sometimes referred as "the iron triangle"), quality, risk and resources.

Add new comment

You must have JavaScript enabled to use this form.

Filtered HTML

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <blockquote> <code> <ul> <ol> <li> <dl> <dt> <dd>
  • Lines and paragraphs break automatically.

Plain text

  • No HTML tags allowed.
  • Web page addresses and e-mail addresses turn into links automatically.
  • Lines and paragraphs break automatically.